Home Health Dodgy finance, lacking infrastructure: Over 200 ailing well being centres on UP govt radar

Dodgy finance, lacking infrastructure: Over 200 ailing well being centres on UP govt radar

0
Dodgy finance, lacking infrastructure: Over 200 ailing well being centres on UP govt radar

[ad_1]

From a constructing with no doorways and home windows to 1 the place stairs are lacking; initiatives whose funds are below a cloud; the place building work is deserted as a result of the company has misplaced curiosity. These are a number of the key the reason why greater than 200 neighborhood well being centres (CHCs) and first well being centres (PHCs) in 52 Uttar Pradesh districts are caught, some from way back to 2005, data accessed by The Indian Express below the Right to Information Act exhibits.

Indeed, most of those centres are languishing from earlier than the Yogi Adityanath authorities got here to energy in 2017, and the UP authorities’s well being division has flagged alleged monetary irregularities, ongoing inside inquiry, or the necessity for a probe by a Special Investigative Team in round 90 such centres (see adjoining interview).


The PHC in Azamgarh’s Kaptanganj space is getting used as a makeshift residence by personnel of the native police station. Vishal Srivastav

According to data out there till August 2023, 86 CHCs and 132 PHCs commissioned between 2005 and 2023 are pending completion. The state has a complete of 970 CHCs and three,976 PHCs throughout 75 districts. As many as 178 or 81.6% of the centres had been commissioned earlier than the Yogi authorities got here to energy.

The well being division has additionally highlighted the extent of completion of every undertaking (desk 1), and the 12 months by which they had been commissioned (desk 2).

A PHC is the primary level of contact between the village neighborhood and the medical officer, meant to offer healing and preventive healthcare to the agricultural inhabitants. They are established and maintained by state governments below the Minimum Needs Programme or Basic Minimum Services Programme, and are presupposed to be manned by a medical officer supported by paramedical and different workers.


An below building major well being centre in Bijnor’s Bhikkawala village. Gajendra Yadav

CHCs are a step increased, serving as referral centres for 4 PHCs and offering amenities for obstetric care and specialist consultations. A CHC is required to be staffed by 4 medical specialists – surgeon, doctor, obstetrician/gynaecologist and paediatrician – supported by paramedical and different workers. It usually has 30 beds with one OT, X-ray, labour room and laboratory amenities.

Information accessed below RTI by The Indian Express reveals the important thing causes behind the stalling of 218 PHCs and CHCs:

  • In round 90 unfinished initiatives, the well being division has highlighted alleged “financial irregularities”, ongoing inside inquiry, or an SIT (Special Investigation Team) probe. In all these instances, greater than 90 % of the quantity that was allotted for building has been spent. While inside inquiries are ongoing, one of many seven businesses tasked with the development – the Rajkiya Nirman Nigam – has advisable an SIT probe.

The PHC in Azamgarh’s Kaptanganj space is getting used as a makeshift residence by personnel of the native police station. Vishal Srivastav

  • In one occasion, the well being division notes: “The building has no doors, windows and the floor is incomplete.” This specific CHC was commissioned in 2006-07 in Ervakatra in jap Uttar Pradesh. A complete of Rs 2.24 crore was allotted, which has been spent, and the federal government has already rejected the revised estimate.
  • On the standing of a CHC in Raniganj Kaithola of Pratapgarh, commissioned in 2014-15, the division notes: “The building does not have stairs or ramp to go from the first floor to the second floor.” While 94 % of the allotted cash has been spent, 60 % of progress has been made.
  • “Affected by financial irregularities. The doors, windows, electric fixer in the buildings are partially complete,” notes the well being division on the standing of a CHC in Azamgarh’s Mohammadpur, commissioned in 2007-08. A complete of Rs 3.02 crore was launched, and regardless of over 96 % of the funds being spent, solely the primary ground of the primary constructing has been completed, data present.
  • On the standing of a CHC in Dapsaura of Fatehpur, which was alloted in 2014-15 and handed its completion deadline in June 2021, the division notes: “Due to high expenditure by the construction unit, internal investigation is ongoing. Work stalled. OHT (overhead tank) is incomplete, there are no nets/glasses in the windows of the main building and MO’s (medical officer) residence.”

The PHC in Azamgarh’s Kaptanganj space is getting used as a makeshift residence by personnel of the native police station. Vishal Srivastav

  • “Due to non-completion of work even after the entire amount has been spent, the process of filing chargesheet against the responsible officers is going on at the executing agency level,” notes the division on the standing of one of many oldest commissioned initiatives from 2006-07 in Paras, Gonda district.
  • “On-site inspection was conducted on 06.07.2023. The work of medical officer and category-2 residence septic tanks and soak pits is still in progress. Apart from this, minor defects are being rectified,” notes the division on the standing of a PHC in Amaujaspur in Sultanpur district, commissioned in 2018-19, which was declared full.

An below building major well being centre in Bijnor’s Bhikkawala village. Gajendra Yadav

  • “The doors installed have to be replaced. The approach road has to be repaired. The floor of the overhead tank is broken,” notes the division on the standing of two PHCs in Bijnor district, commissioned in 2018-19.
  • On the standing of a CHC in Sultanpur, the division notes: “An FIR has been lodged by the executing agency against its JE (junior engineer) and AE (assistant engineer) on 20.03.2015. The work is stalled.” The undertaking was commissioned in 2008-09.

At an under-construction PHC in Bijnor’s Sheikhpura. Gajendra Yadav

  • “The construction/executing agency is not taking interest in completing the work. The balance amount of Rs 70.26 lakh was released on 22.11.2022,” notes the division on the standing of a PHC in Bhadari, Pratapgarh district, commissioned in 2007-08. Despite spending about 50 % of the allotted cash, the undertaking remains to be on the degree of basis work.
  • “Almost the allocated cost for the medical officer’s residence has been spent and the construction work has been done only up to the chair level. Report has been sought from the construction unit,” famous the well being division on the standing of a PHC in Kudarcoat in Auraiya district, commissioned in 2005-06.
  • Other causes cited by the well being division for the delay embody incomplete wiring; no water provide; unavailability of land; no mesh/glass in home windows, and many others. Records additionally present that even within the case of some “completed” works, irregularities had been discovered throughout on-site inspection.

An below building major well being centre in Bijnor’s Bhikkawala village. Gajendra Yadav

Seven authorities businesses had been tasked with the development – UP Rajkiya Nirman Nigam, UP Housing & Development Board, Construction & Design Services of UP Jal Nigam, Uttar Pradesh Rajya Nirman Sahkari Sangh Ltd, UP Projects Corporation Limited, UP State Construction And Infrastructure Development Corporation Limited, and UP Rural Engineering Department.

The most variety of initiatives are being constructed by the Rajkiya Nirman Nigam (63 CHCs and 66 PHCs), adopted by the Housing & Development Board (36 initiatives) and the Rajya Nirman Sahkari Sangh Ltd (28 initiatives).

In whole, of the Rs 393.80 crore allotted for the development of CHCs, Rs 353.36 crore has already been launched till August 2023, and Rs 305.30 crore spent by building businesses. In the case of PHCs, of the Rs 166.75 crore allotted for building, Rs 160.55 crore has been launched and Rs 129.80 crore spent.

At an under-construction PHC in Bijnor’s Sheikhpura. Gajendra Yadav

Working to complete initiatives in a well timed method: Minister

Uttar Pradesh Deputy Chief Minister Brajesh Pathak, who additionally holds the well being portfolio, advised The Indian Express that the state authorities is cognizant of alleged monetary irregularities in some under-construction PHCs and CHCs, and motion has already been initiated.

In response to a questionnaire, Pathak mentioned, “SIT investigation has been ordered by the current government against officials of the executing agency concerned, UP Rajkiya Nirman Nigam Limited. Based on the findings of the SIT investigation, UP Rajkiya Nirman Nigam Limited is taking action against the guilty officials at their own level.”

 

At an under-construction PHC in Bijnor’s Sheikhpura. Gajendra Yadav

UP Rajkiya Nirman Nigam Limited is dealing with 63 CHCs and 66 PHCs which can be but to be accomplished.

Most Read

1
Mela director wept as Aamir Khan insisted on doing a ‘vulgar’ scene, Kajol refused film as she had ‘reservations’ about actor 
2
Leo box office collection day 6: Thalapathy Vijay’s blockbuster is now the biggest film in the Lokesh Cinematic Universe, the fourth-biggest Tamil film in history

Explaining the plan to finish initiatives which can be caught, Pathak mentioned, “It has been decided by the Cabinet that some of the financial burden will be borne by the Rajkiya Nirman Nigam Limited and some by the Health Department, so that work can be completed in a time-bound manner. Action is being taken accordingly.”

The unfinished initiatives embody 40 commissioned below the present BJP authorities within the state. On that, Pathak mentioned, “The works which are currently under construction are being closely monitored and action is being taken to complete them on time so they can be made operational to the public soon.”

“To complete the projects on time, administrative and financial approvals are being issued in a timely manner and funds are being allocated accordingly. The projects are being continuously monitored by the government,” mentioned Pathak, including that that is to make sure monetary irregularities don’t occur sooner or later and initiatives are completed on time.

[adinserter block=”4″]

[ad_2]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here